Communication with M-Bus
A43/A44 242 2CMC48001M0201
User Manual Revision: C
01 FD A5 00 0F ;Interval length 15 minutes
01 FF AB 00 01 ;Subinterval length 1 minute
94 20 A9 FF F9 D1 00 00 00 00 00 ;Current demand (storage number 0) for
1:st maximum active T2 power. VIFE A9 -> data in W with 2 decimals. Data
= 0 W
0E ED EB 00 00 15 00 16 08 14 ;Date/time stamp for maximum given
above: 16:th of august 2014, 00:15:00
9E 40 FD E1 A2 FF F9 D9 00 24 05 00 00 00 00 ;Current demand (storage
number 0) for 1:st maximum input 1 counter sliding demand. Data =
524hex = 524 pulses per hour
0E ED EB 00 00 34 00 16 08 14 ;Date/time stamp for maximum given
above: 16:th of august 2014, 00:34:00
0E ED EB FF F0 00 06 42 00 16 08 14 ;Date/time stamp for end of
measurement period. Will always be current date and time for the
currently pending period, in this case 16:th of august 2014, 00:42:06
1F ;Dif 1F -> More data exists
9F 16 ;Checksum and stop byte
System sends out request UD2:
10 5B FE 59 16
Meter sends out data telegram 4:
68 CE CE 68 08 00 72 34 12 00 00 42 04 20 02 B5 00 00 00 ;Data header
01 FD A5 00 0F ;Interval length 15 minutes
01 FF AB 00 01 ;Subinterval length 1 minute
54 A9 FF F9 D1 00 2C 3D 00 00 ;Demand with storage number 1 for 1:st
maximum total active power import, VIF A9 -> data in W with 2
decimals. Data = 3D2C hex = 156.60 W