FEP630, FEH630 ELECTROMAGNETIC FLOWMETER | OI/FEP630/FEH630-EN REV. D 45
NOTICE
If the O-ring gasket is seated incorrectly or damaged, this
may have an adverse effect on the housing protection class.
Follow the instructions in Opening and closing the housing
on page 23 to open and close the housing safely.
Observe the following points when connecting to an electrical
supply:
Lead the power supply cable into the housing through the
top cable entry.
Lead the cables for signal inputs and signal outputs into
the housing through the middle and, where necessary,
bottom cable entries.
Connect the cables in accordance with the electrical
connection. If present, connect the cable shielding to the
earthing clamp provided.
Use wire end ferrules when connecting.
After connecting the power supply to the dual-
compartment housing, terminal cover
2 must be
installed.
Close unused cable entries using suited plugs.
Change from two to one column

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB ProcessMaster FEP630 series and is the answer not in the manual?

ABB ProcessMaster FEP630 series Specifications

General IconGeneral
BrandABB
ModelProcessMaster FEP630 series
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals