EasyManua.ls Logo

ABB rec670 - Signals in Double-Breaker Arrangement

ABB rec670
658 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
For a busbar grounding switch on bypass busbar C, these conditions are valid:
789OPTR (bay 1)
BB_DC_OP
VP_BB_DC
EXDU_BB
en04000510_ansi.vsd
AND
AND
AND
789OPTR (bay n)
. . .
. . .
. . .
VP789TR (bay 1)
VP789TR (bay n)
EXDU_BB (bay 1)
EXDU_BB (bay n)
. . .
. . .
. . .
. . .
. . .
. . .
ANSI04000510 V1 EN-US
Figure 164: Signals from bypass busbar to busbar grounding switch
14.4.7.3 Signals in double-breaker arrangement
M15053-83 v4
The busbar grounding switch is only allowed to operate if all disconnectors of the bus
section are open.
en04000511_ansi.vsd
Section 1
Section 2
A1A2_DC(BS)
B1B2_DC(BS)
BB_ESBB_ES
DB_BUS
(WA1)A1
(WA2)B1 B2
A2
DB_BUS
ANSI04000511 V1 EN-US
Figure 165: Busbars divided by bus-section disconnectors (circuit breakers)
To derive the signals:
Signal
BB_DC_OP All disconnectors of this part of the busbar are open.
VP_BB_DC The switch status of all disconnectors on this part of the busbar are valid.
EXDU_BB No transmission error from any bay that contains the above information.
These signals from each double-breaker bay (DB_BUS) are needed:
Section 14 1MRK 511 401-UUS A
Control
402 Bay control REC670 2.2 ANSI
Application manual

Table of Contents

Other manuals for ABB rec670

Related product manuals