GUID-8E4978FA-E9CF-48EC-810B-2794A7809282 V1 EN-US
Figure 33: Cancelling operation
If the control operation is not successful, the Control failed message
appears. This can happen, for example, if opening is not enabled before
the open command is executed. More details can be seen via Control/
Monitoring/Control command/Command response.
Information
Control failed
GUID-A4472778-842A-466D-BE83-8CF1F3B0564A V1 EN-US
Figure 34: Control failed message
The time between selecting the object and giving a control
command is restricted by an adjustable time-out. When an object is
selected, the control command has to be given within this time.
6.2.2 Controlling with closing delay
Close delay mode and Close delay need to be set to be able to control objects with
the closing delay.
The closing operation from the LHMI can be delayed by a predefined period of
time.
1.
Press
to close the selected object.
If there are several controllable objects, select the object and press
to confirm the selection.
2.
To confirm the operation, select Yes and press .
After the control operation is confirmed, the delay is activated.
Cancel the control by pressing any key when the delay is active.
2NGA000823 A Section 6
Operating procedures
REX610 49