10. For Smoke detecon sampling systems, perform the following
Measure the response me of all sampling points using
smoke placed at each sampling point.
Check the back-up power supply capacity.
Check the operaon of alarm sengs and indicators.
Check operaon of remote indicaon of alarm and fault
signals.
Check the operaon of airow failure indicators.
Check the operaon of the system (signal) failure indicators.
Check the isolate/reset funcons.
Check the fault and alarm test facilies.
11. Test each ancillary funcon by operang the alarm zone facility(ies), associated with the ancillary
funcon.
Yes No N/A
12. Alarm Signalling
Check that the master alarm facility is able to receive the
alarm signal by operang each alarm zone facility.
Check that the master alarm facility iniates an alarm to the
re control staon equipment.
Check that both the primary and secondary power sources
are of a suitable type and capacity.
Perform a oat voltage check according to the baery
manufacturer's recommendaon to ensure that the charger
type and seng is correct.
Check that all alarm zone facilies have been correctly labelled and
that the alarm zone is immediately apparent from the labelling.
Check the 'as-installed' drawings are marked up, are consistent with
the installaon and the operator's manual is relevant to the
installaon.
Ensure the results of these tests are recorded in the system logbook.