4 Initial set-up and programming
4.1 Initial set-up
First check the following before initial set-up:
– Are all cables connected correctly?
– The power supply is always in operation after the AC mains has been connected and the
AC breaker switched on.
Notice!
Remove the protective dust cover label from the top of the power supply.
Final power connections
1. Switch the AC breaker on.
2. Ensure that there are no power-related trouble conditions.
3. Ensure that the AC LED indicator on the power supply turns on steady before you
connect the battery terminals to the power supply.
4. Connect the battery cable leads to the batteries and the power supply.
Warning!
Injury due to electricity
Risk of injury in the event of short circuit. Ensure the correct polarity!
Connecting the batteries
4.2 Programming
Programming is performed with the program RPS for MAP. A PC or laptop with Windows XP
SP3, Windows VISTA or Windows 7 is required for this. At least 256 MB RAM is needed. A
mouse is recommended for operation of the program.