Figure 54: ESD Grounding Ports on the Front of the Cisco Nexus 7018 Chassis
ESD grounding port1
Installing the Cable Management Frame
After you have fully installed the Cisco Nexus 7018 switch chassis in the rack or cabinet (see the Installing
the Chassis, on page 99), you can install the cable management frame on the front of the chassis.
When you install the cable management frame, you attach four cable management assemblies to the chassis
and then attach a top hood to the top two cable management assemblies and the chassis.
To install the cable management assemblies on the Cisco Nexus 7018 switch chassis, follow these steps:
SUMMARY STEPS
1. Attach a lower cable management assembly (800-31343-01) onto the two hooks that protrude from the
lower half of the left rack-mount bracket that is attached to the Cisco Nexus 7018 switch chassis, and
Cisco Nexus 7000 Series Hardware Installation and Reference Guide
108
Installing a Cisco Nexus 7018 Chassis
Installing the Cable Management Frame