Functional Test, on Ground
98-158751-C Chapter 6: Verification 6-3
6.3 Functional Test, on Ground
6.3.1 Before you start
The system must be activated before performing this test. For further details see
Activation of airtime services on page 5-49.
6.3.2 Check list for functional test on ground
The following list provides some of the most important checks to perform after power-up,
but other additional checks may be relevant for the specific installation.
If you already know that certain interfaces or services are not going to be used, it is not
necessary to perform tests on these specific interfaces or services.
Item Description of Check Reference
Value/
Comment
CSDU LEDs Check that the Power LED is
green
Check that the Fail/Pass LED is
green
Check that the Logon LED is
green
MCDU
headsets #1 to
#3
Make an aircraft to ground call AVIATOR 700S
User Manual [7]
Make a ground to aircraft call AVIATOR 700S
User Manual [7]
Ethernet Connect to the Internet from a
laptop, using the Ethernet AISD
1 / EFB 1 connection. .
AVIATOR 700S
User Manual [7]
Connect to the Internet from a
laptop, using the Ethernet
PIESD 1 / Cabin 1 connection. .
AVIATOR 700S
User Manual [7]
ACARS /
AFIS / CMU
Send a test message and verify
the reply or request for weather
data and verify the data is
downloaded. Both is done from
the CDU / MCDU.
CDU / MCDU
Manual [7]
Table 6-2: Check Sheet: Functional test, on Ground