SiBE041102_A Pump Down Operation
Trial Operation and Field Settings 137
1. Pump Down Operation
Outline In order to protect the environment, be sure to conduct pump down operation when relocating or
disposing the unit.
Detail 1) Remove the valve caps from the liquid stop valve and the gas stop valve.
2) Carry out forced cooling operation.
3) After 5 to 10 minutes, close the liquid stop valve with a hexagonal wrench.
4) After 2 to 3 minutes, close the gas stop valve and stop the forced cooling operation.
Refer to page 138 for forced cooling operation.
Gas stop valve
Valve cap
Close
Liquid stop valve
Service port
(R13628)
Hexagonal
wrench

Table of Contents

Other manuals for Daikin FTXN35KEV1B

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Daikin FTXN35KEV1B and is the answer not in the manual?

Daikin FTXN35KEV1B Specifications

General IconGeneral
BrandDaikin
ModelFTXN35KEV1B
CategoryAir Conditioner
LanguageEnglish

Related product manuals