JT40/JT40 All Terrain Operator’s Manual Transport - 115
Load
Tie Down
Points
Tiedown points are identified by tiedown decals. Securing to trailer at other
points can damage machinery.
Procedure
Loop a transport chain around each tie down point. See chart below for correct distances between tiedown
ends. Make sure tiedowns are tight before transporting.
NOTICE:
• Wrenches can open after engine shutdown. Ensure that any downhole tool or pipe in wrenches is
attached to spindle or removed before transport.
• Use Grade 7-3/8” (18.7 cm) transport chain to secure drilling unit.
IMPORTANT: If hauling unit without pipe box, remove remaining pipe in drill frame chute.
Distance U.S. Metric
A greater than 18” greater than 45.72 cm
B less than 50” less than 127 cm
C greater than 10” greater than 25.4 cm