Installation
Eaton ePDU G3 Operation Manual P-164000277—Rev 1 www.eaton.com/ePDU 21
Figure 18. Attaching the Clip Feet and Cage Nuts
5. ePDU away from the rail (offset). Position and lock two cage nuts far enough apart to stabilize the top
and bottom of the ePDU when mounted on the rail. Insert the cage nuts into the square rail hole with a
flat-blade screwdriver.
6. Locate the two clip feet and two screws (supplied). Turn the straight part of the bracket 90° (see
Figure 19).
7. Position one mounting clip foot at a cage nut and secure the mounting clip foot to the rail with a screw.
R
epeat for the second mounting clip. Tighten the screws.
Figure 19. Attaching the Rotated Clip to the Rail
8. Snap the ePDU into the mounting clip feet. When you hear a clicking sound for each mounting clip foot,
the ePDU is secure.
9. Continue to “Grounding the ePDU” on page 23 if you are installing a ground screw and grounding cable.
O
therwise, go to “Network and Environmental Ports” on page 24.