Risk to life caused by an electric shock
Connection to a socket without protective conductor
− Connecting the machine to sockets without protective conductor can lead
to life-threatening injuries caused by an electric shock.
• Only operate the machine on sockets with a protective conductor (PE).
Risk of injury
Improper modifications to the machine
− Improper modifications to the machine can lead to injuries.
• Do not make any unauthorised changes to the machine.
• Only use spare parts and accessories that have been approved by
Eltra GmbH!
The following conditions must be met before commissioning the machine:
• The machine has been set up, see “Setting up”.
• The reagent tubes have been filled, see “Filling the reagent tube”.
• The machine has been connected to the PC, see “Connecting the machine to the PC”.
• The gas supply has been established, see “Establishing the gas supply”.
• The power supply has been established, see “Establishing the power supply”.
Commission the machine as follows:
1. Switch on the PC and start the ELEMENTS software.
(a current version of the “ELEMENTS software” is supplied on a USB stick or has been
preinstalled on your PC)
2. Switch on the carrier gas.
3. Switch on the compressed air supply.
4. Turn the analyzer to Position 1 on the main switch , see Pos. (10) in “Front”.
5. Wait until the machine has reached the operating temperature .
The machine has been commissioned.
The analyzer is ready for the analysis after approx. 30 to 45 minutes when the cell temperature
(base lines) has stabilized and the catalyst furnace has reached operating temperature.