EDA 2530 Commissioning Procedure for Cable and Wireless Access
1/153 22-FGC 101 0239/2 Uen Rev J 2010-04-01
© Ericsson AB 2010
Commercial in confidence
3 (200)
Contents
1
Introduction............................................................................................7
1.1 Objective.................................................................................................. 7
1.2 Scope ...................................................................................................... 7
1.3 Safety Procedures ................................................................................... 7
1.4 Static Sensitive Device Handling Precautions......................................... 8
1.5 Optical Device Precautions ..................................................................... 8
1.6 Inspection/Cleaning Procedure For Optical Connectors.......................... 8
1.7 Commissioning Test Records.................................................................. 8
1.8 Required Information For Commissioning ............................................... 9
1.9 Documentation Change Request ............................................................ 9
2 EDA 2530 MSAN Equipment............................................................... 11
2.1 General Equipment Description............................................................. 11
2.2 Equipment Overview ............................................................................. 11
2.3 Rack And Subrack Description.............................................................. 14
2.3.1 Rack ...................................................................................................... 14
2.3.2 EDA 2530 Subrack ................................................................................ 14
2.4 Subrack Composition ............................................................................ 15
2.4.1 Composition Rules ................................................................................ 15
2.4.2 EDA2530E Standard Configuration for CWA Parent and Stand Alone
Shelf ...................................................................................................... 16
2.4.3 Network Interface Units ......................................................................... 18
2.4.4 Subscriber Interface Units ..................................................................... 20
2.4.5 Subrack Connection Units ..................................................................... 23
2.4.6 Fan Tray (151-2984/02)......................................................................... 32
3 Resources ............................................................................................ 33
3.1 Documentation ...................................................................................... 33
3.2 Tools...................................................................................................... 33
3.3 Test Equipment ..................................................................................... 33
3.3.1 PC Connection Cables for Commissioning............................................ 34
3.4 Test Cables ........................................................................................... 35
3.4.1 RS232 Serial Cable Set (151-2502/01) ................................................. 36
3.5 Local Craft Terminal (LCT) Installation.................................................. 37
3.5.1 Removal of Old Issue of EDA Hub Software ......................................... 37
3.5.2 Installation of Local Operator Software on P.C...................................... 37
3.5.3 Install Application Software From CD ROM........................................... 38
3.5.4 LCT 07.02.05 – Known Issue with Java Version 1.6 ............................. 39
4 Commissioning Requirements........................................................... 41
4.1 Description Of Testing Activities............................................................ 41
4.2 Test Records ......................................................................................... 41
4.3 Preliminary Checks................................................................................ 41
4.3.1 Equipment Positioning........................................................................... 41
4.3.2 Card Equipping...................................................................................... 41
4.3.3 Cabling .................................................................................................. 42
4.3.4 Power Supply and Grounding Connections........................................... 43
4.4 Earthing And D.C. Supply Checks......................................................... 44
4.5 Power Supply Connection Unit Check................................................... 45