Commissioning
28 © Festo Didactic GmbH & Co. • MPS
Please download the full project into the PLC and test the full process.
Information
Please make sure that the PC is connected to the PLC with the communication cable,
the power supply of the station is on, air-pressure of around 5 bar is available at
each station, the emergency switch is deactivated (if available) and the CPU-switch
is in STOP position. Make sure that the PLC memory is empty (delete).
Instructor: Show how to delete the contents of a CPU using the switch of the CPU.
Let all the participants try it several times. Explain them where to find the project
and what the project name is. Explain them step-by-step how to download a
project to the PLC. Develop the process sequence on the white board first this
means, what is the process and how to start it. Which are the Control Panel
functions. Tell the participants, in which subdirectory they are able to find the
programs à in the following screen shots, the project is located in:
C:\SIEMENS\STEP7\MPSVERSC
Basically all screen shots and PLC-projects are based on the software
STEP 7 Version 5.1 other versions may be a little bit different, but the used
functions and screen shots within the following projects are mostly the same!!!!
Planning
Please follow the description of the in instructor carefully step-by-step. Use the
NOTICE field to write down the single steps to proceed.
The time to finish this project should be around 1,0 hours.
1.7 Commissioning
Download Project
and Test