The installation of the FHE-250 Hot Water Boiler should be carried out by competent personnel in
accordance with all relevant safety regulations. It is the responsibility of the installer to ensure that
these regulations are complied with.
WARNING
Maintenance on the burner assembly requires that the area directly in front of the boiler must
not be obstructed with pipework or equipment which would interfere with the removal of
the complete burner unit. Care should be taken on installation of the boiler to ensure this area
remains clear of obstructions.
SECTION 2 - INSTALLATION
2.1
GENERAL
2.2
SITING
(Reference should be made to Utilisation Procedures as stated in IGE/UP/10 Part 1
Communication 1676, and in particular to Section 5, Location of Appliances).
The boiler house should be sufciently large to allow easy and safe access to all parts of the boiler
for operational and maintenance purposes.
1. The boiler must stand on a oor which must be at, non-combustible, level and of a suitable
load bearing capacity to support the weight of the boiler (when lled with water) and any
ancillary equipment.
2. The boiler must not be tted outside.
3. Install so that all system components are protected from water (dripping, spraying, rain etc)
during boiler operation and service.
4. Minimum clearance for access should be maintained at 600 mm at the front and at least one
side of the boiler/modular installation.
5. Ensure all labels on the boiler will be fully visible for maintenance and inspection.