3
It is essential that the commissioning procedures listed below are carried out either by a
Fulton Service Engineer or by an authorised professional who will have the necessary experience
and testing equipment to ensure that the installation is not only correct, but is operating safely and
at optimum efciency.
1. Verify with authorised personnel that the gas lines have been purged. Do not proceed without
verication.
2. Familiarise all personnel on all aspects of boiler use, safety, and contents of this manual. This
includes, but is not limited to, the use of the controls, lighting/ring the boiler, and shutdown
procedures.
3. Review the unit-specic control schematics, and follow appropriate instructions.
WARNING
Before commissioning the boiler, verify with authorised personnel that the gas lines have been purged.
!
WARNING
Commissioning/Start up by a non-Fulton authorised person will void the product warranty.
!
!
WARNING
Whilst effecting the required gas soundness test and purging air from the gas installation, open all
windows and doors, extinguish naked lights and DO NOT SMOKE.
1. The whole of the gas installation, including the meter, should be inspected and tested for
soundness and then purged in accordance with the recommendations of the relevant standards
listed on Page 2. In IE refer to I.S.820:2000.
3.4
COMMISSIONING THE BOILER
3.4.1
ELECTRICAL INSTALLATION
3.4.2
GAS INSTALLATION
3.4.3
FLUE COMMISSIONING
1. Check to ensure electrical safety should be carried out by a competent person.
2. ALWAYS carry out the preliminary electrical system checks, i.e. earth continuity, polarity,
resistance to earth using a suitable meter.
Prior to initial ring of the boiler, the ue must be checked for leaks.
This is done by BOTH of the following methods:
Visual Inspection
Check joints between all ue sections for quality of seals. Where the ue passes through the structure
of the building use your judgement as to the integrity of this section of the ue.
Smoke Test
With the ue capped, the drain stabiliser pipe (if tted) blanked and a smoke generator inserted into
the ue, there should be no smoke visible from the ue.
If either of these tests fail or at any time during boiler operation there is doubt about the integrity of
the ue, shut down the boiler and contact Fulton Ltd immediately.
Note: Flues that are designed to operate with positive pressure should be tested to the latest regulations.