FULTON FHE-250 - 1.4 SAFETY

FULTON FHE-250
78 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
FHE-250 MANUAL 09 2014 ISSUE 2
Page 2
1
y Air Inlet Ducting Kit
For FHE-500 and above:
y Water and Gas Header Assembly - Packaged
y Water and Gas Header Assembly c/w Valves - Packaged
y Flue Header Kit
Note: Please contact Fulton Ltd for further details of all optional extras.
1.3
OPTIONAL EXTRAS
1.4
SAFETY
Current Gas Safety (Installation and Use) Regulations or rules in force.
The appliance is suitable for installation in any EU country and should be installed in accordance with
the rules in force.
In the UK, the installation must be carried out by a Gas Safe Registered Engineer or in IE by a
competent person. It must be carried out in accordance with the relevant requirements of the:
y Gas Safety (Installation and Use) Regulations
y The appropriate Building Regulations either The Building Regulations, The Building Regulations
(Scotland), Building Regulations (Northern Ireland).
y The Water Fittings Regulations or Water by-laws in Scotland.
y The Current I.E.E. Wiring Regulations.
Where no specic instructions are given, reference should be made to the relevant British Standard
Code of Practice.
In IE, the installation must be carried out by a Competent Person and installed in accordance with the
current edition of I.S.820:2000 “Non Domestic Gas Installations”, the current Building Regulations
and reference should be made to the current ETCI rules for electrical installation.
The boilers have been tested by a notied body and conform to EN656 and EN15417 for use with
Natural Gas. Detailed recommendations are contained in the following Standards and Codes of
Practice:
BS. 5854 Flue and ue Structures in Buildings.
BS. 6644 Installation of gas red hot water boilers of rated inputs between 70 kW and
1.8 MW (net) (2nd and 3rd family gases).
BS. 6880 Low temperature hot water heating systems of output greater than 45 kW.
Part 1 Fundamental and design considerations.
Part 2 Selection of equipment.
Part 3 Installation, commissioning and maintenance.
IGE/UP/1 Soundness testing and purging of industrial and commercial gas installations.
IGE/UP/2 Gas installation pipework, boosters and compressors on industrial and
commercial premises.
IGE/UP/10 Installation of gas appliances in industrial and commercial premises.

Table of Contents