Connect a packed column with
bypass lines/valves
Follow the instruction below to connect a pre-packed column with bypass lines/valves
to ÄKTAprocess.
ActionStep
Connect tubing between the column bottom and the system valve marked
COLUMN BOTTOM.
1
Connect tubing between the column top and the system valve marked
COLUMN TOP.
2
Set the system column valves to the UpFlow position.3
Using the pump, fill the system with an appropriate liquid for column instal-
lation.
4
When the system, including the tubing connected to the column, is filled
with liquid, stop the pump.
5
Use the manual valves on the column to change from bypass to in-line.6
Final considerations
Once the column is connected, the following should be taken into consideration.
Make sure to activate the system alarm(s) again after the filling sequence.
When the pump is started, the system must be in Column UpFlow position.