GE
D
IRECTION 5535208-100, REV. 2 LOGIQ E9 SERVICE MANUAL
Chapter 8 Replacement procedures 8 - 139
8-6-8-2 Calibration and adjustments
No calibrations or adjustments are needed after this part replacement.
8-6-8-3 Verification
Perform the following steps to verify that the product is functioning as intended after this replacement:
1.) Verify that all screws removed earlier have been installed.
2.) If finished, connect cables and Probes removed earlier.
3.) Power up the system to verify that it operates as intended.
8-6-8-4 Functional Checks
Perform the following functional checks to confirm the system is operational before returning the system
to the customer.
If all are successful, include the following debrief script: LOGIQ E9 Service Manual, Direction
5535208-100, Rev. 2. Equipment passed all required checks and is ready for use.
Table 8-89 Upper Operator Panel / Touch Panel Assembly installation Functional
Checks
See:
Section
Functional Check Debrief Script
4-2-2 Power ON/Boot Up
LOGIQ E9 Service Manual, Direction
5535208-100, Rev. 2. Equipment passed all
required checks and is ready for use.
4-2-3 Power shut down
4-3-5 B-Mode Checks
4-3-7 System CFM and PWD Checks
4-3-10 Basic Measurements
7-5-17-2 Touch Panel Calibration Verification
7-5-12-11 I/O Board Tests