396
Cutting and Enlarging Connecting
Open All Valves
Checkup for Air Leakage
Vacuumizing
Cutting or enlarging pipes should be
proceeded by installation personnel
according to the operating criterion if the
tube is too long or are opening is broken.
1. Connecting circular terminals:
The connecting method of circular terminal is shown
in the Fig. Take off the screw, connect it to the
terminal tier after heading it through the ring at the
end of the lead and then tighten it.
2.Connecting straight terminals:
The connection methods for the circular terminals
are shown as follows: loosen the screw before
putting the line terminal into the terminal tier, tighten
the screw and conrm it has been clamped by
pulling the line gently.
3.Pressing connecting line
After connecting line is completed, press the
connecting line with clips which should press on the
protective sleeve of the connecting line.
Vacuumize from the stop valve of outdoor
units with vacuum pump. Refrigerant sealed
in indoor machine is not allowed to use for
vacuumization.
Open all the valves of outdoor units. [NB:
oil balancing stop valve must be shut up
completely when connected one main unit.]
Check if there is any leakage at the
connecting part and bonnet with hydrophone
or soapsuds.
Connecting
circular terminals:
Correct
pressing
Terminal tier
Pressing clip
Wrong
pressing