4.1.2 Installation Environment Check
Check the site requirements one by one, and start installation only after all
requirements are met. The Company will not be liable for any consequences in the
case that the installation environment does not meet the requirements.
Mark the safe zone: Use red caution belts to delimit a safe zone, clean up
obstacles in the safe zone, and place construction signs and warning signs in
prominent positions.
4.2 Installing the ESS
4.2.1 Determining the Installation Position of the ESS
Prerequisites
● The site requirements are met.
● Check and adjust the height of the concrete platforms to ensure that the
height
dierence between the upper surfaces of all platforms does not exceed
5 mm.
Ensure that the concrete platforms meet requirements.
● Determine the installation position and orientation of the ESS based on site
conditions.
Procedure
Step 1 Determine the reference points for installing the ESS on the concrete platforms.
Mark the reference points using a marker.
Step 2 On the basis of the reference points, mark the mounting positions for the four
corner
ttings of the ESS using an ink fountain and a long soft measure tape.
When marking the positions for corner ttings, ensure that the four lines form a
rectangle.
LUNA2000-2.0MWH Series Smart String ESS
User Manual 4 Installation
Issue 08 (2022-11-15) Copyright © Huawei Technologies Co., Ltd. 94