Figure 5-12 Routing the ground cables in from the bottom
----End
5.3 Installing DC Power Cables
Prerequisites
● The ESS is not powered on.
● The DC power cables have been pre-buried according to the specications.
● The OT/DT terminals have been crimped according to the specications. For
details, see C Crimping an OT or DT Terminal.
Procedure
Step 1 Remove the protective cover
Figure 5-13 Removing the protective cover