6 Checking Before Power-On
Item No. Check Item Acceptance Criteria
General
inspection
1 Equipment
appearance
The equipment is intact and free from rust or paint
ake-o. If paint akes o, repaint the equipment.
The labels on the equipment are clear. Damaged
labels must be replaced.
2 Cable appearance Cable sheathings are properly wrapped and not
damaged.
Cable hoses are intact.
3 Cable connections Cables are connected in the designed positions.
Terminals are prepared as required and securely
connected.
Labels on both ends of each cable are clear and
specic, and attached in the same direction.
4 Cable layout Electrical and ELV cables are routed separately.
Cables are neat and tidy.
Cable tie joints are evenly cut without burrs.
Cables are placed properly and reserve some slack
at bending points to avoid stress.
Cables are routed neatly without twists or
crossovers in the cabinet.
5 Switch The DC LV Panel switch is set to OFF.
The battery rack switch is set to OFF.
ESS 1 Installation The installation meets the design requirements.
The ESS is level, and each door can be opened
properly.
2 Grounding Each ESS has at least two ground points and is
grounded securely with a ground resistance of 0.1
ohm or less.
LUNA2000-2.0MWH Series Smart String ESS
User Manual 6 Checking Before Power-On