If the doors of the ESS cannot be opened and closed properly, please refer to the rst
question in chapter 11, 'How do I Level the ESS When Doors Cannot Be Opened or
Closed'.
4.3 Installing Components
● Ensure that the ESS is not powered on.
● The installation personnel have taken safety protection measures, for example,
wearing insulated gloves and shoes.
4.3.1 Installing Copper Bars Between Battery Packs
Prerequisites
The battery cabin door is open.
Procedure
Step 1 Take out the copper bars from the battery cabin.
Figure 4-9 Positions of the copper bars
(1) Desiccan (Montmorillonite desiccant, 500
g)
(2) Copper bar
LUNA2000-2.0MWH Series Smart String ESS
User Manual 4 Installation
Issue 08 (2022-11-15) Copyright © Huawei Technologies Co., Ltd. 104