Commissioning
Order of installation
70
Lenze • BA v200-C v800-.C • 1.1
5 Commissioning
The interfaces of the devices are accessible on the rear side. All supply leads and all required
data leads have to be connected before commissioning.
Attention
The device must be switched off before connecting or disconnecting any cables in order to
prevent damage to the electronics!
The device may only be switched on after acclimatising to the ambient temperature in order
to avoid condensate accumulation. Make sure to meet the permissible voltage for this device.
After switching off and before switching on you must wait for at least 5 seconds.
Note
The shielding of a data cable must always be connected with the connector housing (EMC).