Lucent Technologies Lineage
®
2000 ECS/GPS Battery Plant J85500G-2
Issue 6 May 1999 Installation 4 - 11
1. Test Enable/disable equalize charge feature.
2. Test Enable/disable rectifier restart feature.
3. Test HV shutdown level(s).
4. Test BD alarm levels.
5. Test other optional circuit packs.
Load turn-up Turn on and adjust all rectifiers for normal operation according
to the Rectifier manual.
WARNING:
Before applying power to any individual load, follow the
powering up instructions as provided in the associated load
equipment documentation.
Connect all loads, one at a time, by turning on the load circuit
breakers. If a circuit breaker trips immediately when turned on,
this may be due to inrush current and does not necessarily
indicate a fault condition. Attempt to close the circuit breaker a
second time. If the breaker trips again, check the wiring to the
load circuit.
Installation
p
rocedures
f
or
p
lant
g
rowth
As your power needs evolve, equipment may be readily added to
the battery plant to provide any of the following.
expanded controller features
additional rectifier capacity
increased battery capacity (associated with additional
rectifier capacity)
additional load circuits
Procedures for adding controller features, rectifiers and batteries
to an operating plant are described in the installation sections of
the associated subsystem manuals. The procedure to add load
circuits, since they are part of the dc distribution subsystem, is
described below.