14.
Power on the chassis by pressing the power button at the front.
It takes approximately five minutes and 30 seconds for the node to boot.
15. Perform the configuration steps.
If the H610S node is part of a NetApp HCI installation, use NetApp Hybrid Cloud Control to configure
the storage resource. See Expand NetApp HCI storage resources.
If the H610S node is part of a SolidFire all-flash storage installation, configure the node using the
NetApp Element software user interface (UI).
Contact NetApp Support for assistance.
Find more information
NetApp HCI Resources page
SolidFire and Element Software Documentation Center
Replace power supply units
Each chassis includes two power supply units for power redundancy. If a power supply
unit is faulty, you should replace it as soon as possible to ensure that the chassis has a
redundant power source.
What you’ll need
You have determined that the power supply unit is faulty.
You have a replacement power supply unit.
You have verified that the second power supply unit is operating.
You have an electrostatic discharge (ESD) wristband, or you have taken other antistatic precautions.
About this task
The replacement procedure applies to the following node models:
Two rack unit (2U), four-node NetApp HCI chassis
2U H610C compute chassis
One rack unit (1U) H615C compute chassis
1U H610S storage chassis
In the case of H610C, H615C, and H610S, the terms "node" and "chassis" are used
interchangeably because node and chassis are not separate components, unlike in the
case of the 2U, four-node chassis.
Alarms in the VMware vSphere Web Client provide information about the failed power supply unit, referring to it
as PS1 or PS2. In a NetApp HCI 2U, four-node chassis, PS1 refers to the unit on the top row of the chassis
and PS2 refers to the unit on the bottom row of the chassis. You can replace the faulty power supply unit while
your chassis is powered on and working, as long as the redundant power supply unit is functioning.
Steps
1. Locate the faulty power supply unit in the chassis. The LED on the faulty unit displays amber.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the NetApp HCI and is the answer not in the manual?

NetApp HCI Specifications

General IconGeneral
Product TypeHyperconverged Infrastructure (HCI)
Data ServicesData protection, encryption
Connectivity10 GbE, 25 GbE, 40 GbE, 100 GbE
Hypervisor SupportVMware vSphere
Management NodeIncluded in the solution
Storage MediaSSD and HDD
Node TypesCompute nodes, storage nodes
Storage ProtocolsiSCSI
Data ReductionDeduplication, compression, thin provisioning
High AvailabilityBuilt-in redundancy