4-6
Alarms
AN2016 Cabinet User Guide Rel 1.0 Standard May 1999
Procedure 4-1
Connecting the alarms
Use this procedure to connect the alarms to be reported to the ABM #1 shelf.
Requirements
You need the following tools and materials:
wire-wrap tool
solid wire 24 AWG
Action
Step Action
1
Select the alarms to be reported to the ABM #1 shelf and the input telemetry
points to be used (see Table 4-1 and Figure 4-2).
2
Refer to procedure 9.6, ”Changing the telemetry input description”,
(NTP 323-3001-032). The Engineering and Ordering Information is part of
AccessNode, Release AN16 or later.
3
Use the solid wire 24 AWG to wire wrap the alarms from the input telemetry.
Note:
After you connect the alarms, provision them so that the appropriate
label shows up at the alarm monitoring facility.
—end—