User Guide Rel 1.0 Standard May 1999
3-1
Installation guidelines 3-
The procedures in this chapter describe how to install the AN2016 Cabinet.
Procedures in this chapter
Table 3-1 lists the installation procedures in the order in which you must
perform them.
Table 3-1
Installation procedures
Action Details
Unpacking the cabinet Procedure 3-1 on page 3-2
Selecting the site Procedure 3-2 on page 3-3
Preparing a concrete mounting pad for the cabinet Procedure 3-3 on page 3-4
Preparing the cabinet for installation Procedure 3-4 on page 3-12
Routing the cables to the mounting pad Procedure 3-5 on page 3-18
Mounting the cabinet on the pad Procedure 3-6 on page 3-21
Leveling the cabinet Procedure 3-7 on page 3-24
Installing the cable in the split sleeve Procedure 3-8 on page 3-26
Connecting the earth ground to the cabinet Procedure 3-9 on page 3-28
Installing the surge arrestor Procedure 3-10 on page 3-32
Connecting ac power Procedure 3-11 on page 3-34
Installing batteries Procedure 3-12 on page 3-38
Installing battery cables from an external vault Procedure 3-13 on page 3-43