6.4.4 Softener time clock delayed programming
6.4.4.1 Setting the regeneration time
Set the regeneration time in the system.
1. Press MODE until display position point to the Regeneration Time icon.
2. Press and hold or until the Programming icon appears.
3. Set the time with or .
4. Press MODE to go to the next parameter, or press and hold to
validate the selection and return to the service mode.
6.4.4.2 Setting the salt amount
Set the salt amount in the system.
1. Press MODE until display position point to the Salt Amount icon.
2. Press and hold or until the Programming icon appears.
3. Set the salt amount with or , 50 to 290g/l (metric).
4. Press MODE to go to the next parameter, or press and hold to
validate the selection and return to the service mode.
6.4.4.3 Setting the number of days between regenerations
Set the number of days between regenerations in the system.
1. Press MODE until display position point to the Days Between
Regenerations icon.
2. Press and hold or until the Programming icon appears.
3. Set the number of days between regenerations with or , 1 to
30days.
4. Press MODE to go to the next parameter, or press and hold to
validate the selection and return to the service mode.
6.4.4.4 Days to regeneration
Info
The days to regeneration indicate the remaining days until next regeneration and
cannot be adjusted.
1. Press MODE until display position point to the Days To Regeneration
icon.
2. The display shows the remaining days until next regeneration.