R5 SOLID AIS System
INSTALLATION
7000 118-200, C2 Page 26
When the R5 SOLID has been installed according to the procedures described in previous
sections, it is recommended to make a first functional check of the system. Check the
following things to ensure that the R5 SOLID is fully functional.
Check the Transmitted Own Ship Data view to make sure that the configured data
is sent by the R5 SOLID on the VHF link, refer to section 4.10 “View Transmitted
Own Ship Information” for more information.
Make sure that there are no unexpected active alarms in the alarm list, see section
4.18 “Alarms”.
Perform a communication test to ensure that the R5 SOLID can send and receive
messages from other AIS transponders. Refer to section 4.25 “Communication Test” for