EasyManua.ls Logo

SAJ Suntrio-TL Series - 5.5 Connecting the Electricity Grid (AC); 5.5.1 Conditions for the AC Connection; 5.5.2 AC Connection procedure

SAJ Suntrio-TL Series
54 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
User Manual
18
User Manual
5.5 Connecting the Electricity Grid (AC)
5.5.1Conditions for the AC Connection
You must comply with the connection requirements of your network operator
.
Residual Current monitoring
The inverter is equipped with an integrated all-pole-sensitive residual-current monitoring unit.
The inverter can automatically differentiate between residual currents and normal leading leakage
currents.
If an external RCD or residual-current device (RCMU breaker) is strictly required, you must use
a switch that trips at a residual current 100mA≤ Ifn ≤300mA.
The external RCMU breaker should be installed between inverter and Grid. No load should not
connected to the inverter directly.
Connection of a Second Protective Conductor
In some installation countries, a second protective conductor is required in order to prevent a
contact current in the event of failure of the original protective conductor.(See section 5.5.3)
IEC standard 62109 requirements:
Installation of the protective earthing conductor at AC terminal with a cross-section of at least
10mm
2
(copper), or 16mm
2
(aluminum).
UTE C15-712-1:2010 requirements:
The inverter body conductive accessories must be connected to the equipotential bonding
via a conductor with a minimum cross-section of 6mm² Cu or equivalent and to the protective
conductor at AC terminal.
5.5.2 AC Connection procedure
1)Strip the cable with the length 12mm, be careful NOT to nick conductors.

Related product manuals