2 - CN-Series Hardware Installation
This section describes how to install a CN-Series system for a minimum Federation that contains two
OmniCube systems. As your storage and performance needs increase, you can add more OmniCube systems
to a Federation.
General Guidelines for Installing Hardware in a Rack
SimpliVity recommends that you install the hardware in a rack according to the following guidelines:
Follow all safety guidelines stated in the rack's documentation, particularly when installing components
into the locations at the top of the rack.
Make sure the rack meets the requirements.
Install systems in the same rack when possible.
Install systems in a rack starting from the bottom of the rack.
Always install a CN-Series systemin a horizontal position, or you void your warranty and support
contract.
Related Topics
Rack Requirements on page 20
Task 2—Installing Each CN-Series System in a Rack on page 23
Tasks for Installing the Hardware
After you install the CN-Series system in a rack and connect power and network cables, you can create a
datacenter within vCenter Server and deploy each CN-Series system as an OmniCube in a Federation.
Complete these tasks to install the hardware for a Federation containing two OmniCube systems:
Task 1Performing the Pre-Installation Tasks on page 16
Task 2Installing Each CN-Series System in a Rack on page 23
Task 3Connecting the Power Cables on page 25
Task 4Connecting the Network Cables on page 26
Task 5Configuring IPMI for Remote Management on page 27
Task 6Powering on the System on page 30