Before initial start-up, check that the following point have been dealt
with:
All instructions followed, in above sections of this chapter
grounding conductor resistance and substitute leakage currents
checked according threshold of owner usage.
No impermissibly high side -acting forces impacting on the guide
tube unit.
Entire stroke area unobstructed so that linear actuators cannot be
driven onto a fixed object.
All cables secured against pinching and trapping, and properly
connected
Electrical supply secured
Operating device connected to the control unit.
Initial start-up
After the installation check has been completed, you can start up the
linear actuators MAX: with the LED on the operating light green,
press the corresponding operating button of the operating device.
Prior to first operation, a professional electrician must perform and
document the following tests and readings:
Visual condition check
Functional check of operating features and safety features
Reading of leakage currents
Reading of insulation resistance
!
Note!
Additional information concerning inspections and
readings. ( Maintenance, chapter 8) .
40

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SKF Matrix Series and is the answer not in the manual?

SKF Matrix Series Specifications

General IconGeneral
BrandSKF
ModelMatrix Series
CategoryController
LanguageEnglish

Related product manuals