2. Turn ON DC switch.
3. Switch ON the battery. Turn ON DC isolator between
battery & inverter.
4. Turn ON AC circuit breaker between the inverter GRID port
& GRID.
5. Turn ON AC circuit breaker between the inverter LOAD port
& critical load.
6. Inverter should start to operate now.
6.4 Initial setup
You need to set the following parameters before inverter starts
to operate.
Table. 6-1 set the parameter
If you are connected to the server or
using the App, the time is set to the
local time automatically
3) Safety parameter
import
Refer to the country code table
below and select country and code.
With the Input Channel
Configuration you define if PV and /
or batteries are connected and in
what configuration. If an input
channel is not used, select (Not use)
If a battery is connected to BAT1
input, select “Bat Input1”, otherwise
“Not Use”
if a second battery is connected to
BAT2 independently, select “Bat
Input2”
If one battery is connected in
parallel to BAT1 and BAT2, select
“Bat Input1”, otherwise “Not Use”
if PV strings are connected to PV1
independently, select “PV Input 1”,