Chapter 3 Installing the Server Into the Sun Rack 900 Cabinet 57
8. Check that the server is level and centered on the tray.
Use a level and adjust the server position if necessary.
9. Tighten the eight M4 screws that secure the server to the tray assembly.
Restoring the Server
1. A qualified service technician must install the CPU/Memory boards and fan trays
that were removed before you installed the server into the cabinet.
See the Sun Fire V890 Server Service Manual for installation instructions.
2. If you removed the server’s side doors, replace them.
Caution – Avoid keeping the server’s doors open for extended periods while the
system is operating. Server doors must be closed to prevent automatic thermal
shutdown.
3. Close both of the server’s side doors securely.
4. Slide the tray assembly into the cabinet.
5. Install the power supplies that you removed before you installed the server into
the cabinet.
See the Sun Fire V890 Server Service Manual for installation instructions.
!