Inspection before Commissioning
table 3-1 Requirements before commissioning
Item
Description
Location
The charger is correctly mounted at a place that is convenient
for operation and maintenance.
Charger The charger is firmly and securely installed.
Cable
Cables are correctly and firmly connected, and are adequately
protected from damage.
Current leakage
protection
The AC input’s current leakage protection switch is reasonable.
Clearance
The charger has sufficient cooling space and there is no other
stuff or components are left on the top of the charger.
It is recommended to update the firmware of the charger to the latest version be-
fore charging to ensure optimal charging performance.
Step 1 Ensure that all requirements are met before commissioning.
Step 2 Turn on the current leakage protection switch of the AC input.
Step 3 Power on the charger.
The blue LED blinks slowly which indicates the charger is in standby mode.
- - End