4. Set load/unload ramp times to at least 60 seconds.
5. Set base load level to 30% of rated load.
6. Shut down the unit by removing the Auto and Run with Load Inputs.
7. Set synchronizer to run mode.
8. Start unit with an Auto and Run with Load Input.
9. Monitor synchroscope status menu.
a. Verify action of synchronizer.
NOTE
If using Process 4–20mA input, Set Process Reference to Proper Level.
10. After generator breaker closes to the mains, monitor Generator Status
menu.
a. Monitor KW load on unit.
b. Monitor KVAR/PF on unit.
1. As set by reactive load control setting.
11. Adjust load control gain, stability, derivative for stable load control.
12. Once satisfied with load control operation, switch to process control (if
applicable).
13. Confirm ramp to process reference level.
a. Tune process control for best response.
14. Remove run with load input to unit.
a. Verify unload ramping.
b. Verify unload trip point.
c. Verify generator breaker opens.
d. Verify cooldown timer (if reached).
15. Set crank repeats, base load reference, process reference, load ramp
times, and load control mode as required for proper operation.
This concludes the Mains Parallel Master Setup.
No Parallel and Slave Setup
Use the following instructions for setup of No Parallel Applications, and Slave
unit applications.
1. Set unit for LOM on mains under frequency.
2. Set unit for check mains breaker disabled.
3. Set for dead bus closing enabled.
4. Remove mains PT and mains CB Aux input by opening mains breaker if
necessary.
5. Start unit with auto switch input.
6. Unit will start and close generator breaker to bus.
a. Verify dead bus closing.
b. Apply load to unit using load bank or plant load as applies.
c. Calibrate CT readings if needed.
7. If in a multi unit system, repeat previous steps for all units. Set all units to be
tested synchronizers to check mode prior to start.
8. The unit currently on the bus carrying the load will act as a synchronizing
reference for the other units.
9. Verify voltage matching, phase relationships of additional units by
monitoring the synchroscope status menu.
a. Verify voltage levels across generator breakers.