PoE Configuration Example 345
The Ethernet 1/0/1 and Ethernet 1/0/2 ports of Switch A are connected to
Switch B and an AP respectively; the Ethernet 1/0/8 port is intended to be
connected with an important AP.
The PSE processing software of Switch A is first upgraded online. The remotely
accessed PDs are powered by Switch A.
The power consumption of the accessed AP is 2,500 mW, and the maximum
power consumption of Switch B is 12,000 mW.
It is required to guarantee the power feeding to the PDs connected to the
Ethernet 1/0/8 port even when Switch A is under full load.
Networking diagram
Figure 104 Network diagram for PoE
Configuration procedure
# Upgrade the PSE processing software online.
<SwitchA> system-view
[SwitchA] poe update refresh 0290_021.s19
# Enable the PoE feature on Ethernet 1/0/1, and set the PoE maximum output
power of Ethernet 1/0/1 to 12,000 mW.
[SwitchA] interface Ethernet 1/0/1
[SwitchA-Ethernet1/0/1] poe enable
[SwitchA-Ethernet1/0/1] poe max-power 12000
[SwitchA-Ethernet1/0/1] quit
# Enable the PoE feature on Ethernet 1/0/2, and set the PoE maximum output
power of Ethernet 1/0/2 to 2500 mW.
[SwitchA] interface Ethernet 1/0/2
[SwitchA-Ethernet1/0/2] poe enable
[SwitchA-Ethernet1/0/2] poe max-power 2500
[SwitchA-Ethernet1/0/2] quit
# Enable the PoE feature on Ethernet 1/0/8, and set the PoE priority of Ethernet
1/0/8 to critical.
[SwitchA] interface Ethernet 1/0/8
[SwitchA-Ethernet1/0/8] poe enable
Switch A
Network
Eth1/0/2
Eth1/0/1 Eth1/0/8
Switch B AP AP