EasyManua.ls Logo

ABB PQFM - Inspection on Site - Verification of the Active Filter after Installation

ABB PQFM
229 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Manual Power Quality Filter PQFM Commissioning instructions 179
Project:
LV Active Filters PQF
Issued by:
Commissioning report
Dat
e:
Page 2 of 7
8.11.2 Inspection on site – verification of the active filter after installation
Ambient conditions
OK/NOK
Check the ambient temperature (< 4C/104°F) (if > 4C/104°F, derating is required)
Check the installation altitude (< 1000m/3300ft) (if > 1000m/3300ft, derating is required)
Check the ventilation (room and enclosure)
Ensure that no sources of conductive dust are present
Intern
al connections
(a)
Disconnect the filter from the supply including the auxiliary circuit (disconnection recommended
by upstream protection)
Remove filter internal protection grid
DC capacitor voltage low enough to operate safely (DC voltage measurement)
Change auxiliary transformer primary tap setting to correspond to network nominal voltage
rating
(b)
Wiring of main and auxiliary circuit
Tightness of all electrical connections
Connectors properly plugged in
Fixation of components
Remove anti-corrosion capsules installed at the inside of the filter door (if still present)
Clearances
Cooling fans running freely
Address of each filter unit in a multi-unit system set to a different value and main’ master has
the lowest address
(c)
CAN bus terminated properly on each unit of a multi-unit system
(c)
CAN bus communication cable between the different units properly installed
(c)
Earth interconnection between the different units installed
Installation
(a)
Check cross-sections of power supply cables (L1-L2-L3)
Check cross-section of protective conductors (PE) (> = 16 mm²) connected to each cubicle and
between cubicles.
Check tightness of conductor fixations
The material of busbars, terminals and conductors must be compatible (corrosion)
Check the setting and operation of the protective apparatus
Check rated current of the power supply cable fuses (if applicable)
Check the cabling of the digital I/O (if present)
Check the voltage in accordance with the specification
Check the phase rotation order at the filter power terminals (with filter auxiliaries off)
(clockwise)
( b)
For multi-unit filters, check that the same phases are connected to the same filter power
terminals for the individual units
Check visually the current transformers
- Ratio
- Installed at the right side (feeding-side of the active filter)
For multi-unit filters, check that the CTs of all units are cabled in a daisy chain fashion with return
path
( d)
Remove all jumpers of all current transformers (CTs and SCTs)

Table of Contents