ANSI07000188 V1 EN-US
Figure 59: Test of RTC with I/O
11.18 Basic IED functions
SEMOD52026-1 v1
11.18.1 Parameter setting group handling SETGRPS
M11369-2 v4
Prepare the IED for verification of settings as outlined in section "Preparing for test" in this chapter.
11.18.1.1 Verifying the settings
M11369-4 v5
1. Check the configuration of binary inputs that control the selection of the active setting group.
2. Browse to the ActiveGroup menu to achieve information about the active setting group.
The ActiveGroup menu is located on the local HMI underMain menu/Test /Function status/
Setting groups /ActiveGroup
The ActiveGroup menu is located on the PCM600 under Main menu/Test/Function status/
Setting groups /ActiveGroup
3. Connect the appropriate dc voltage to the corresponding binary input of the IED and observe the
information presented on the local HMI.
The displayed information must always correspond to the activated input.
4. Check that the corresponding output indicates the active group.
Operating procedures for the PC aided methods of changing the active setting groups are
described in the corresponding PCM600 documents and instructions for the operators within the
SCS are included in the SCS documentation.
1MRK 504 165-UUS Rev. J Section 11
Testing functionality by secondary injection
Transformer protection RET670 291
Commissioning manual