Rev. 0, 2010.02.09 ERECTION WORK and TRANSPORT Kap.4 , Seite 11 of 12
GRZ-2698569-v1-Erection.FM
4.6 Cold test
Prerequisites The following utilities must be available:
• Electric power
• Water
Lubrication
• First filling of lubricant and recording of all further lubrication
procedures according to the section on "Lubrication" in the
MAINTENANCE chapter.
Cold test Cold test is to be carried out together with the customer's authorized
representative.
The work steps listed in the cold test log shall be carried out for the cold
test, and documented.
Final inspection The customer and the erection work supervisor shall conduct a final
inspection of the installation on completion of the cold tests.
Logs The following logs are issued after completion of the ISO cold test
• Cold test log
• Log of completion of erection work.
Logs:
/ATTACHMENT/LOGS AND BLOCK DIAGRAMS
CAUTION
Machine may be damaged if inappropriate oil or grease grades are
used as first filling.
Only use oils or greases with the properties listed in the lubrication
schedules.