Medium-consistency pump MC
STANDARD, C-01-000000
Rev. 0, 2010.02.09 OPERATION Kap.6 , Seite 3 of 12
GRZ-2698572-v1-Operation.FM
6.5 Checks after initial start-up
The following items must be checked after initial start-up:
required amount of sealing water and required sealing water pressure
to the shaft seal
bearing temperature and vibration (in continuous operation)
pump flow rate
6.6 Normal operation
While the pump is in operation the operating personnel should record the
relevant data. (Shift record and data sheets)
Activities during normal operations
once per shift The following work has to be performed per shift in normal operation.
CAUTION
If there are any unusual noises, it is essential to look for the cause
without delay and then eliminate the problem!
DANGER
Do not operate without all safety devices ON.
Component Activity
Medium-consistency pump, complete Visual check (sealing water, leaks, etc.)
Vibrations
Tab. 6-2 Activities to be performed every shift