7.3 Shift/Daily Checkout
Perform the procedure contained on the Daily Checkout card at every shift change, power-up, and machine set-up change.
During continuous machine run periods, this checkout should be performed at intervals not to exceed 24 hours.
A Designated Person or Qualified Person (as defined in the
Glossary
on page 95) must perform the procedure. A copy of
checkout results should be recorded and kept in the appropriate place (for example, near or on the machine, in the
machine’s technical
file).
Refer to the procedure detailed on the Daily Checkout card (Banner p/n 113361 for SLS.. models, P/N 118173 for SLSC..
models) in the documentation packet included with the receiver. If the Daily Checkout card is missing, contact Banner
Engineering or download a copy of the card at
http://www.bannerengineering.com
.
7.4 Semi-Annual (Six-Month) Checkout
Perform the procedure on the Semi-Annual Checkout card every six months following System installation, or whenever
changes are made to the System (either a new
configuration of the EZ-SCREEN or changes to the machine).
A
Qualified Person (as defined in the
Glossary
on page 95) must perform the procedure. A copy of checkout results
should be recorded and kept in the appropriate place (for example, near or on the machine, in the machine’s technical
file).
Refer to the procedure on the Semi-Annual Checkout card (Banner p/n 113362) in the documentation packet included with
the receiver. If the Semi-Annual Checkout card is missing, contact Banner Engineering or download a copy of the card at