RPC SERIES OWNER’S MANUAL
DETAILED OPERATION AND CONFIGURATION
________________________________________________________________________________
52
From the Outlet Configuration Menu, select
#3, “Outlet Power-up Delay.” The unit
responds:
To set delay, enter number of outlet, CR to exit
Outlet power-up delays (in seconds):
1) . . . Outlet 1 : 0
2) . . . Outlet 2 : 0
3) . . . Outlet 3 : 0
4) . . . Outlet 4 : 0
5) . . . Outlet 5 : 0
6) . . . Outlet 6 : 0
7) . . . Outlet 7 : 0
8) . . . Outlet 8 : 0
Enter Request >
Enter the number of the outlet to set a
power-up delay, followed by <cr>. The unit
responds:
Outlet Name: Outlet 1
Enter delay (seconds) >
Enter the amount of time (up to 599
seconds) to elapse before power is applied to
the outlet. The RPC Series redisplays the
power-up delay status reflecting the change.
Name Outlets
“Name Outlets” allows the user to customize
outlet name(s) to identify individual pieces
of equipment attached to the RPC. From the
RPC’s configuration menu, the user can
change any or all outlet names to outline a
unique set-up.
Default outlet names are
Outlet 1, Outlet 2, Outlet 3 . . . Outlet 8.
From the “Outlet Configuration” Menu
select #4, “Change Outlet Name,” followed
by <cr>. The RPC displays the following
menu:

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the BayTech RPC-2 and is the answer not in the manual?

BayTech RPC-2 Specifications

General IconGeneral
BrandBayTech
ModelRPC-2
CategoryControl Unit
LanguageEnglish