45Bend-Tech Dragon A400
Maintenance & Troubleshooting
Control Box
10
3. Mount New Control Box
Before mounting the new Control Box, the Installer will need to remove the red Breakout Board
located in the upper left hand corner of the new Control Box. Carefully pull the Breakout Board
out of its mount on the motor drivers. It should remain connected to the door of the Control Box
new Control Box so the Mounting Bolts can be fed through the mounting holes in the Control
Box and the Rail Support Leg. Once in position with a Mounting Bolt fed through both parts,
Box to tighten the Mounting Bolts securely.
4. Reinstall the Break Out Board
After mounting the Control Box, reinstall the Breakout Board. Position the Breakout Board
over the motor drivers and, applying even pressure, carefully press the Breakout Board into its
sockets on the motor drivers. Ensure the Breakout Board is fully seated on the motor drivers.
Take care not to alter any of the white dip switch settings as these are preset at the Bend-Tech
manufacturing facility for optimum performance.
5. Place the Powered Gate Driver Box
The Powered Gate Driver Box should be placed on top of the main Control Box. The Powered
Gate Driver Box is secured with Velcro which is pre-installed on the Control Boxes.
6. Control Box Connections
Transfer all cable, wiring and compressed air connections from the old Control Box to the new
Control Box. Bend-Tech recommends starting at either the top or bottom of the old Control Box
and transfer each connection individually. Using this method will avoid misconnections.
The Powered Gate Control Box will have a separate Powered Gate Driver Box
attached to it. This control box contains the motor driver for the Powered Gate. The
Powered Gate Driver Box is placed on top of the main Control Box once it is mounted
to the third Rail Support Leg.