September 2021
Installation, Operation and Maintenance Manual
VCIOM-01249-EN Rev. 0
Storage and Pre-Installation 7
Section 2: Storage and Pre-Installation
Figure 5
Figure 6
2.3 Checks to be Performed Before Installation
• Make sure the valve to be motorised is the appropriate one for coupling to
the actuator.
• The electrical supply cables must be suitable for the power rating (see the test
certicate that comes with the actuator).
• Gather the right tools for the assembly and for setting the actuator controls.
If a long storage period has occurred, before reinstalling the actuator, please:
• Check the status of the O-ring seals.
• Check the installation of the plugs or cable glands on the cable entries.
• Check whether the enclosure covers or the actuator body are cracked or broken
• Check the oil level in the actuator and top up if necessary.
• Put the batteries back into place (see Section 11.3, Maintenance - Lithium
battery change).