What to do next
To install the front mezzanine module, see Installing the Front Mezzanine Module, on page 25
Installing the Front Mezzanine Module
Use the following procedure to install the front mezzanine module. This procedure applies to the following
modeules:
Front mezzanine blank (UCSX-X10C-FMBK)
Compute Pass Through Controller (UCSX-X10C-PT4F)
MRAID Storage Controller Module (UCSX-X10C-RAIDF)
Before you begin
To install the front mezzanine module, you need a T8 screwdriver and a #2 Phillips screwdriver.