COMMISSIONING CHECK LIST
GENERAL
" All equipment ordered by the customer is installed.
" The unit is level and secure.
" The mains and control wiring are complete and the circuit breaker and GPO are turned ON.
" All Controller functions for the appliance operate.
" All electrical or gas connections are to manufacturers specifications and the relevant electrical or gas
standards and codes.
U
NIT - DUCTED EVAPORATIVE AIR CONDITIONER
" The water supply line has been flushed to clear swarf and debris and is free of leaks.
" The tank is free of foreign matter and debris and the water isolating tap is turned ON.
" Water drainpipe work is completed and sealed.
" The water basin fills with water and the float valve closes correctly when the water level is 65-70mm
below the overflow level.
" The water pump operates correctly when turned ON at the controller.
" The Dialflo water bleed rate is adjusted to suit local water conditions.
" The Superclean Dump Valve (option). The tank drains correctly when unit turns off.
" The fan deck is correctly located and the fan blade spins freely.
" The fan operates through the entire speed range.
" The minimum fan speed is correctly set.
" Water distribution is even with the filter pads fitted and the air conditioner operating pump and fan.
U
NIT ā DUCTED HEATING
" Electrical polarity of the power outlet is correct.
" Heater is installed away from sources of dust and fumes (i.e. pool chlorine/petrol etc).
" Gas leaks checked for, none present.
" Flue outlet pipe complies with limits given / code and is sealed waterproof.
" Combustion air meets requirements (internal, under floor).
" Fan speed set is correct.
" Burner pressure is correct.
" Mounting pad/platform complies with requirements / codes.