11 Overload tests
During the commissioning of the machine, in the final test, we
carried out the following overload tests. During the same, we
tested S15 stability and structural resistance.
Overload tests shall be carried out only on the first test of the ma-
chine: these tests are unique. In no other occasion shall you carry out
tests with the same loads used in the overload tests.
Overload
Test
Load
(Kg)
Boom position
Move-
ment
Out-
come
Ra
y
(m)
B
oom
//
1
200 (PN)
+
160 (CP)
5,90 Horizontal // Lateral OK
2
200 (PN)
+
160 (CP)
5,90 Horizontal // lateral OK
NOTES
PN: nominal capacity.
CP: test load.